Harish's local planning and building subcommittee approved Vilar group's building plan for a logistics centre on plots 510 and 511 in the Harish South employment district on Monday, 23 November 2026.
According to a statement from the Shas faction in Harish, the building will have two floors and about 17,500 square metres. Construction is expected to take one and a half to two years once a building permit is issued; the project still has to complete licensing before work can begin.
A Vilar International presentation puts construction costs at about NIS 219 million and projects rental income of about NIS 17.8 million a year at full occupancy, roughly NIS 1.48 million a month, with completion targeted for 2028-2029. The figures are company forecasts.
Source: Yedioth Harish, 23 November 2026.